MIP45 Executive Spell: Technical Delay - 2021-04-16 -> 2021-04-19

A last-minute technical issue was found while testing this week’s spell to add MIP45 and activate it for LINK-A. This issue can be resolved, but must be fixed before moving forward. Thus, the spell is now expected to go live no earlier than next Monday, April 19th. A full explanation of the issue that caused this delay will be released at that time.

24 Likes

Thanks for keeping the protocol safe!

12 Likes

Explanation: ESM+End Module Upgrades and Disclosures