Weekly MIPs Update #14

Last Week’s Activity (August 31-September 4)

Monday/Thursday

  • There were no polls or votes that happened last week related to a Monthly Governance Cycle.
  • Announced September’s Governance cycle is set to begin on September 7.
  • Weekly MIPs Update on the Thursday Governance and Risk Call.

This Week’s Activity (September 7 - September 11)

Monday

  • September’s Governance Cycle officially began on Monday, September 7.
  • The Formal Submission period is September 7 to September 9.
    • This period is when MIPs/Subproposals in the RFC phase are proposed to enter the governance cycle.

Thursday

  • The Governance Facilitator will perform the Submission Review on the weekly Governance and Risk call to determine which of the formally submitted MIPs/Subproposals may be put forth for Inclusion Polls on Monday, September 14.

Next Week’s Activity (September 14 - September 18)

Monday

  • Inclusion Polls for the formally submitted MIPs/SPs will be proposed on Monday, September 14, and will run until September 17 at noon EST.

Thursday

  • During the weekly Governance and Risk Call, the Governance Facilitator will perform the Inclusion Poll Review and confirm which of the proposed MIPs/Subproposals should be included in the Monthly MIPs Governance Poll the following Monday, September 21.

Other News

Collateral Onboarding

  • The PAXUSD and USDT Executive Vote passed on September 5 and is available for execution tomorrow, September 8. Once executed, both collateral types will be added to the Maker Protocol.
  • Next month’s planned collaterals types are:
  • September’s Collateral Onboarding Community Greenlight Polls will go live on September 21. See the Collateral Status Index for reference.

Oracles

  • The Executive Vote to Whitelist yEarn Finance on ETH/USD Oracle passed last Thursday.
  • The Executive Vote to add Argent as a Light Feed passed on September 5 and is available for execution on Septemeber 8.
  • The tBTC Oracle Whitelisting Polling Vote will go out tomorrow, September 8.

Maker Protocol Updates

MIPs Update

Proposals in the Conception Phase

MIPs

Subproposals

Proposals in the RFC Phase

Proposals in the Formal Submission Phase (so far)

New and Ongoing Pre-MIP Discussions:


/fin

2 Likes

I think the MIP13c3-SP5 is missing from the list of Proposals in the Conception Phase, right?

The Weekly MIPs update was posted on Tuesday and MIP13c3-SP5 was posted yesterday, so that is why it is not listed. I will make an edit to the update to add it.

1 Like

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.